GP500 Manganese Crushing & Screening plant
Project Showcase
Client:
African Mining & Crushing
Location:
Tshipi Borwa Mine, Northern Cape , South Africa.
Scope of Works:
Installation of Structural Work, Mechanical Equipment, Platework, and Piping
Project Highlights:
Design and Fabrication Phase, which entailed +- 500 Tons of Steelwork, was completed in a mere 5 months.
Total project duration was 9 months, despite the project escalating from a semi-mobile plant to a 20-year lifespan fixed plant.
GP500 is one of the largest cone crushers in South Africa.
Twin plant allows for redundancy, allows the plant to operate at 50% capacity during maintenance periods.
The twin plant design also allows for separation of low grade and high-grade ore.