Upgrade of facilities, successful logistics management, and an emphasis on safety and quality.
1D Tailings Pipeline
Installation of 7.2km of Ø630mm HDPE piping. Commitment to quality and safety, while logistics to remote areas expertly managed, ensuring timely completion.
1D Dry Iron Ore Crushing & screening plant
Delivered a dry crushing and screening plant in 8 months, producing -32 All-in Iron Ore. Performance exceeded design with a 1200 TPH throughput.
1D WET IRON ORE WASH PLANT
Follow-up to the 1D-Dry installation, designed to deslime iron ore and achieve 1200 TPH. Completed on time and within budget.
1G Iron Ore Crushing & Screening Plant
State-of-the-art design achieved 2400 TPH, outperforming larger plants. The twin design allows 50% operation during maintenance. Completed in 9 months.
Amanzi quarry conveyors & chutework
Cost reduction was achieved by utilizing existing structures and equipment, and innovative design optimized the conveyor layout for efficient handling.
GP500 manganese crushing & screening plant
The 5-month Design and Fabrication Phase led to a 9-month project upgrading to a fixed plant with the GP500 cone crusher and twin design for redundancy.
Mineral Sizer Introduction - bauxite mine
Designed steelwork and completed installation within 72 hours, enhancing product quality and securing a long-term client relationship.
Mthatha quarry conveyors & chutework
Successfully completed on a demanding schedule, Nautilus optimized the plant beyond the original scope and incorporated adjustable conveyors for future reuse on other projects.
UMK MANGANESE PLANT
Semi-mobile conveyors allowed efficient layout changes, and “dead boxes” minimized wear from manganese ore, ensuring maximum uptime.